According to the best sources available as of September, 2009, the timeline for the transmission line route pertaining to the North Palo Duro Canyon is as follows:

4th Quarter 2009 through 1st Quarter 2010 – Sharyland will prepare CCN filing for preferred and alternative line routes

2nd Quarter 2010 – Sharyland will file CCN applications with PUCT

3rd or 4th Quarter 2010 – PUCT approves CCNs and line routes

1st or 2nd Quarter 2011 – Transmission line construction will begin

2012-2013 – Construction will be completed